firstworkdate - script and chart function

The firstworkdate function returns the latest starting date to achieve no_of_workdays (Monday-Friday) ending no later than end_date taking into account any optionally listed holidays. end_date and holiday should be valid dates or timestamps.

Syntax:  

firstworkdate(end_date, no_of_workdays {, holiday} )

Return data type: integer

Arguments:  

Arguments
Argument Description
end_date The timestamp of end date to evaluate.
no_of_workdays The number of working days to achieve.
holiday

Holiday periods to exclude from working days. A holiday is stated as a string constant date. You can specify multiple holiday dates, separated by commas.

Example: '12/25/2013', '12/26/2013', '12/31/2013', '01/01/2014'